Three workers can paint a fence in \(4\) days. If one more worker joins the team, how many days will it take them to finish the work\(?\) What are the assumptions you need to make\(?\)
CBSE Class 8 Maths · Proportional Reasoning - 2
CBSE Class 8 Maths · Proportional Reasoning - 2
Imagine you and 2 friends are painting a fence together. With 3 people, it takes 4 full days to finish. Now a 4th friend joins to help. More helpers means the job gets done faster! Think of it like carrying heavy bags — extra hands make it quicker. The total work stays the same, just shared among more people. With 4 workers sharing equally, the fence gets finished in only 3 days instead of 4.
Answer: The 4 workers will finish the fence in \( 3 \) days. Assumptions: all workers work equally fast, work equal hours per day, and the total amount of work is unchanged.
This is a problem about inverse proportion. When more workers do the same fixed amount of work, the time needed becomes less. So the number of workers and the number of days are inversely proportional. In inverse proportion, when one quantity increases, the other decreases in such a way that their product stays constant. If \( x \) is the number of workers and \( y \) is the number of days, then \( x \times y \) is always the same value. That constant product represents the total amount of work (measured in worker-days).
For inverse proportion: \( x_1 y_1 = x_2 y_2 \)
The 4 workers will finish the fence in \( 3 \) days. Assumptions: all workers work equally fast, work equal hours per day, and the total amount of work is unchanged.
A common mistake is treating this as direct proportion and increasing the days when workers increase. Since more workers finish the job faster, the days must decrease, so inverse proportion (equal products) must be used, not direct proportion.
The 4 workers will finish the fence in \( 3 \) days. Assumptions: all workers work equally fast, work equal hours per day, and the total amount of work is unchanged.
One common mistake: Students mistakenly use the direct proportion formula \( \frac{x_1}{y_1} = \frac{x_2}{y_2} \) instead of the inverse proportion formula \( x_1 y_1 = x_2 y_2 \), which would give the wrong answer of \( y_2 = \frac{16}{3} \) days.
Answer: The 4 workers will finish the fence in \( 3 \) days. Assumptions: all workers work equally fast, work equal hours per day, and the total amount of work is unchanged.
Question: Five workers can lay tiles in a hall in 6 days. If two more workers join the team, how many days will it take to finish the job? State the assumptions you make.
Solution: We use the concept of inverse proportion between the number of workers and the number of days, keeping total work constant. Total work (in worker-days): \[ \text{Total work} = 5 \times 6 = 30 \text{ worker-days} \] New number of workers after two more join: \[ \text{New workers} = 5 + 2 = 7 \] Let the number of days needed by 7 workers be \( d \). Using the inverse proportion relation: \[ W_1 \times D_1 = W_2 \times D_2 \] \[ 5 \times 6 = 7 \times d \] \[ 30 = 7d \] \[ d = \frac{30}{7} \approx 4\frac{2}{7} \text{ days} \] Assumptions: (1) All workers work at the same rate. (2) Each worker works the same number of hours per day. (3) The workers do not interfere with each other's work.
Answer: \( \frac{30}{7} \) days, which is approximately \( 4\frac{2}{7} \) days.
Question: A group of 8 machines can fill boxes at a factory in 9 hours. If 4 machines break down and stop working, how many hours will the remaining machines take to complete the same job? State the assumptions you make.
Solution: We use the inverse proportion relationship: more machines means fewer hours for the same total work. Total work (in machine-hours): \[ \text{Total work} = 8 \times 9 = 72 \text{ machine-hours} \] Number of machines remaining after 4 break down: \[ \text{Remaining machines} = 8 - 4 = 4 \] Let the number of hours needed by 4 machines be \( h \). Using the inverse proportion relation: \[ W_1 \times D_1 = W_2 \times D_2 \] \[ 8 \times 9 = 4 \times h \] \[ 72 = 4h \] \[ h = \frac{72}{4} = 18 \text{ hours} \] Assumptions: (1) All machines work at the same rate. (2) Each machine runs continuously without any additional breaks. (3) The breakdown of some machines does not affect the efficiency of the remaining machines.
Answer: 18 hours.
Question: Five workers can build a wall in 6 days. If 3 more workers join the team at the start, how many days will it take to finish the wall? State any assumptions you make.
Answer: With 8 workers, the wall will be completed in \( 3\frac{3}{4} \) days (i.e., 3.75 days). Assumptions: all workers work at equal speed, for equal hours each day, and the total work remains unchanged.