Three workers can paint a fence in \(4\) days. If one more worker joins the team, how many days will it take them to finish the work\(?\) What are the assumptions you need to make\(?\)

CBSE Class 8 Maths · Proportional Reasoning - 2

Solution

👶 Simple Explanation

Simple Explanation

Imagine you and 2 friends are painting a fence together. With 3 people, it takes 4 full days to finish. Now a 4th friend joins to help. More helpers means the job gets done faster! Think of it like carrying heavy bags — extra hands make it quicker. The total work stays the same, just shared among more people. With 4 workers sharing equally, the fence gets finished in only 3 days instead of 4.

Answer: The 4 workers will finish the fence in \( 3 \) days. Assumptions: all workers work equally fast, work equal hours per day, and the total amount of work is unchanged.

📖 Workers and Days: An Inverse Proportion Problem

Detailed Explanation

This is a problem about inverse proportion. When more workers do the same fixed amount of work, the time needed becomes less. So the number of workers and the number of days are inversely proportional. In inverse proportion, when one quantity increases, the other decreases in such a way that their product stays constant. If \( x \) is the number of workers and \( y \) is the number of days, then \( x \times y \) is always the same value. That constant product represents the total amount of work (measured in worker-days).

Formula Used

For inverse proportion: \( x_1 y_1 = x_2 y_2 \)

Solution

  1. Step 1: Identify the quantities. Number of workers and number of days are the two quantities. More workers means fewer days, so they are in inverse proportion.
  2. Step 2: Write down the known values. Here \( x_1 = 3 \) workers, \( y_1 = 4 \) days, and \( x_2 = 4 \) workers (one more worker joins). We need to find \( y_2 \), the number of days.
  3. Step 3: Apply the inverse proportion rule, since the product of workers and days stays constant. \[ x_1 y_1 = x_2 y_2 \]
  4. Step 4: Substitute the values. \[ 3 \times 4 = 4 \times y_2 \] This gives \[ 12 = 4 \, y_2 \]
  5. Step 5: Solve for \( y_2 \). \[ y_2 = \frac{12}{4} = 3 \] So it takes 3 days.
  6. Step 6: State the assumptions. We assume that all workers work at the same speed (equal efficiency), that every worker works for the same number of hours each day, and that the total work of painting the fence stays the same.

Final Answer

The 4 workers will finish the fence in \( 3 \) days. Assumptions: all workers work equally fast, work equal hours per day, and the total amount of work is unchanged.

Common Mistake

A common mistake is treating this as direct proportion and increasing the days when workers increase. Since more workers finish the job faster, the days must decrease, so inverse proportion (equal products) must be used, not direct proportion.

🪜 Step-by-step Solution

Step-by-step Solution

  1. Step 1: Recognise the type of proportion. As the number of workers goes up, the number of days comes down (and vice versa). This is inverse proportion — Reason: In inverse proportion the two quantities change in opposite directions, so their product stays constant.
  2. Step 2: List all known and unknown values. Original workers: \( x_1 = 3 \). Original days: \( y_1 = 4 \). New number of workers: \( x_2 = 4 \). Days needed with 4 workers: \( y_2 = ? \) — Reason: Writing values clearly before calculating prevents errors in substitution.
  3. Step 3: Write the inverse proportion equation. \[ x_1 \times y_1 = x_2 \times y_2 \] — Reason: The product of workers and days equals the total work (worker-days), which does not change.
  4. Step 4: Substitute the known values into the equation. \[ 3 \times 4 = 4 \times y_2 \] Simplifying the left side: \[ 12 = 4 \times y_2 \] — Reason: Plugging in numbers converts the formula into a simple one-variable equation.
  5. Step 5: Solve for \( y_2 \) by dividing both sides by 4. \[ y_2 = \frac{12}{4} = 3 \] — Reason: Isolating the unknown gives the number of days the 4 workers need to complete the fence.
  6. Step 6: State the assumptions clearly. All 4 workers must work at the same speed (equal efficiency), every worker must put in the same number of hours each day, and the total area of fencing to be painted must remain unchanged — Reason: The inverse proportion relationship is only valid when these conditions hold.

Final Answer

The 4 workers will finish the fence in \( 3 \) days. Assumptions: all workers work equally fast, work equal hours per day, and the total amount of work is unchanged.

Common Mistake

One common mistake: Students mistakenly use the direct proportion formula \( \frac{x_1}{y_1} = \frac{x_2}{y_2} \) instead of the inverse proportion formula \( x_1 y_1 = x_2 y_2 \), which would give the wrong answer of \( y_2 = \frac{16}{3} \) days.

✍️ Exam-ready Answer

Exam-ready Answer

  1. Step 1: Given: \( x_1 = 3 \), \( y_1 = 4 \), \( x_2 = 4 \), find \( y_2 \).
  2. Step 2: \[ 3 \times 4 = 4 \times y_2 \]
  3. Step 3: \[ y_2 = \frac{12}{4} = 3 \]

Answer: The 4 workers will finish the fence in \( 3 \) days. Assumptions: all workers work equally fast, work equal hours per day, and the total amount of work is unchanged.

➕ More Examples

More Examples

Example 1

Question: Five workers can lay tiles in a hall in 6 days. If two more workers join the team, how many days will it take to finish the job? State the assumptions you make.

Solution: We use the concept of inverse proportion between the number of workers and the number of days, keeping total work constant. Total work (in worker-days): \[ \text{Total work} = 5 \times 6 = 30 \text{ worker-days} \] New number of workers after two more join: \[ \text{New workers} = 5 + 2 = 7 \] Let the number of days needed by 7 workers be \( d \). Using the inverse proportion relation: \[ W_1 \times D_1 = W_2 \times D_2 \] \[ 5 \times 6 = 7 \times d \] \[ 30 = 7d \] \[ d = \frac{30}{7} \approx 4\frac{2}{7} \text{ days} \] Assumptions: (1) All workers work at the same rate. (2) Each worker works the same number of hours per day. (3) The workers do not interfere with each other's work.

Answer: \( \frac{30}{7} \) days, which is approximately \( 4\frac{2}{7} \) days.

Example 2

Question: A group of 8 machines can fill boxes at a factory in 9 hours. If 4 machines break down and stop working, how many hours will the remaining machines take to complete the same job? State the assumptions you make.

Solution: We use the inverse proportion relationship: more machines means fewer hours for the same total work. Total work (in machine-hours): \[ \text{Total work} = 8 \times 9 = 72 \text{ machine-hours} \] Number of machines remaining after 4 break down: \[ \text{Remaining machines} = 8 - 4 = 4 \] Let the number of hours needed by 4 machines be \( h \). Using the inverse proportion relation: \[ W_1 \times D_1 = W_2 \times D_2 \] \[ 8 \times 9 = 4 \times h \] \[ 72 = 4h \] \[ h = \frac{72}{4} = 18 \text{ hours} \] Assumptions: (1) All machines work at the same rate. (2) Each machine runs continuously without any additional breaks. (3) The breakdown of some machines does not affect the efficiency of the remaining machines.

Answer: 18 hours.

🎯 Try a Similar Question

Try a Similar Question

Question: Five workers can build a wall in 6 days. If 3 more workers join the team at the start, how many days will it take to finish the wall? State any assumptions you make.

Solution

  1. Step 1: Find the total amount of work: The total work is measured in worker-days. With 5 workers taking 6 days, the total work is: \[ 5 \times 6 = 30 \text{ worker-days} \]
  2. Step 2: Find the new number of workers: 3 more workers join the original team of 5, so the new number of workers is: \[ 5 + 3 = 8 \text{ workers} \]
  3. Step 3: Use inverse proportion to find the new number of days: Since total work remains the same (30 worker-days), let the new number of days be \( d \). Then: \[ 8 \times d = 30 \] Dividing both sides by 8: \[ d = \frac{30}{8} = 3.75 \text{ days} \] This can also be written as \( 3\frac{3}{4} \) days.
  4. Step 4: State the assumptions: The assumptions are: (1) All 8 workers work at the same rate. (2) Every worker works the same number of hours each day. (3) The total amount of work (building the wall) does not change.

Answer: With 8 workers, the wall will be completed in \( 3\frac{3}{4} \) days (i.e., 3.75 days). Assumptions: all workers work at equal speed, for equal hours each day, and the total work remains unchanged.