\(20\) workers take \(4\) days to complete laying a road. How many days will \(10\) workers take to complete laying the same length of road\(?\)
CBSE Class 8 Maths · Proportional Reasoning - 2
CBSE Class 8 Maths · Proportional Reasoning - 2
Imagine a group of friends cleaning a playground. More friends means the job gets done faster. Fewer friends means it takes longer. Here, 20 workers finish a road in just 4 days. But when only 10 workers show up, there are half as many people doing the same amount of work. So the job takes twice as long. Half the workers means double the days. That is why 10 workers need 8 days to finish the very same road.
Answer: \( 10 \) workers will take \( 8 \) days to complete laying the same road.
This is a problem of inverse proportion. When two quantities are in inverse proportion, one increases as the other decreases, and their product stays constant. Here, if you use fewer workers, they will take more days to finish the same road. So more workers means fewer days, and fewer workers means more days. The total amount of work stays the same, and this total is measured by the product of workers and days.
For inverse proportion: \( x_1 y_1 = x_2 y_2 \), where \( x \) is the number of workers and \( y \) is the number of days.
\( 10 \) workers will take \( 8 \) days to complete laying the same road.
A common mistake is treating this as direct proportion and setting up \( \frac{20}{4} = \frac{10}{y_2} \), which gives \( 2 \) days. This is wrong because fewer workers cannot finish faster. Always check that fewer workers should give MORE days, which signals inverse proportion.
\( 10 \) workers will take \( 8 \) days to complete laying the same road.
One common mistake: Students sometimes apply the direct proportion formula \( \frac{x_1}{y_1} = \frac{x_2}{y_2} \) instead of the inverse proportion formula \( x_1 y_1 = x_2 y_2 \), which gives the wrong answer. Always check first whether the two quantities increase together (direct) or one increases while the other decreases (inverse).
Answer: \( 10 \) workers will take \( 8 \) days to complete laying the same road.
Question: A team of 15 painters can paint a large building in 12 days. If only 9 painters are available, how many days will they take to paint the same building?
Solution: Here, the number of painters and the number of days are in inverse proportion — fewer painters means more days to finish the same work. Using the inverse proportion formula: \( x_1 \times y_1 = x_2 \times y_2 \) Given values: \( x_1 = 15 \), \( y_1 = 12 \), \( x_2 = 9 \), and \( y_2 = ? \) Substituting the known values: \[ 15 \times 12 = 9 \times y_2 \] Simplifying the left side: \[ 180 = 9 \times y_2 \] Solving for \( y_2 \): \[ y_2 = \frac{180}{9} = 20 \] Therefore, 9 painters will take 20 days to paint the building.
Answer: 20 days
Question: A factory employs 24 machines to manufacture a batch of toys in 5 days. Due to maintenance, only 8 machines are working. How many days will it take to manufacture the same batch of toys?
Solution: The number of machines and the number of days required are in inverse proportion — fewer machines means more days to finish the same batch. Using the inverse proportion formula: \( x_1 \times y_1 = x_2 \times y_2 \) Given values: \( x_1 = 24 \), \( y_1 = 5 \), \( x_2 = 8 \), and \( y_2 = ? \) Substituting the known values: \[ 24 \times 5 = 8 \times y_2 \] Simplifying the left side: \[ 120 = 8 \times y_2 \] Solving for \( y_2 \): \[ y_2 = \frac{120}{8} = 15 \] Therefore, 8 machines will take 15 days to manufacture the same batch of toys.
Answer: 15 days
Question: A team of 15 painters can paint a building in 6 days. If only 9 painters are available, how many days will they take to paint the same building?
Answer: 9 painters will take \( 10 \) days to paint the same building.