Detailed Explanation
A ratio tells us how the parts of a mixture are shared. Here the concrete mixture is made of cement, sand, and gravel in the ratio \( 1 : 1.5 : 3 \). This means for every \( 1 \) part of cement, we use \( 1.5 \) parts of sand and \( 3 \) parts of gravel. The total mixture is the sum of all the parts. If we measure each part in bags, then the amount of cement acts like our unit. Once we know how many bags of cement we have, we can find how many bags of sand and gravel go with it, and then add them all together to get the total bags of mixture.
Formula Used
Total mixture parts = cement parts + sand parts + gravel parts, and for a fixed amount of cement: \[ \text{Total bags} = \left( \text{bags of cement} \right) \times \frac{(1 + 1.5 + 3)}{1} \]
Solution
- Step 1: Write down the given ratio of the components. Cement : Sand : Gravel is \( 1 : 1.5 : 3 \). This means each \( 1 \) part of cement is matched with \( 1.5 \) parts of sand and \( 3 \) parts of gravel.
- Step 2: Understand what the given amount of cement means. We have \( 3 \) bags of cement. In the ratio, cement corresponds to \( 1 \) part, so \( 1 \) part equals \( 3 \) bags.
- Step 3: Find the sand needed. Sand is \( 1.5 \) parts, so \[ \text{Sand} = 1.5 \times 3 = 4.5 \text{ bags}. \] This keeps the mixture in the correct ratio.
- Step 4: Find the gravel needed. Gravel is \( 3 \) parts, so \[ \text{Gravel} = 3 \times 3 = 9 \text{ bags}. \]
- Step 5: Add all the components to get the total mixture. \[ \text{Total} = 3 + 4.5 + 9 = 16.5 \text{ bags}. \] We add because the mixture is made by combining cement, sand, and gravel together.
- Step 6: Check using the total-parts idea. Total parts \( = 1 + 1.5 + 3 = 5.5 \). Since \( 1 \) part \( = 3 \) bags, \[ 5.5 \times 3 = 16.5 \text{ bags}, \] which matches our answer.
Final Answer
We can make \( 16.5 \) bags of concrete mixture (using \( 3 \) bags of cement, \( 4.5 \) bags of sand, and \( 9 \) bags of gravel).
Common Mistake
A common mistake is to think the answer is just \( 3 \) bags (the cement amount) or to forget to add the cement itself into the total. Remember the mixture includes cement, sand, and gravel all together, so all three parts must be added.